EurActiv Logo
EU-Nachrichten & Politikdebatten
- durch Sprachenvielfalt -
Bulgaria News
Turkey News
Germany News
Spain News
France News
United Kingdom News
Poland News
Czech Republic News
Slovakia News
Hungary News
Romania News
Serbia News
Greece News
Italy News
Bulgaria Turkey Germany Spain France United Kingdom Poland Czech Republic Slovakia Hungary Romania Serbia Greece Italy
EurActiv.com Réseau

ALLE SEKTIONEN BROWSEN

Sehr geehrte Leserinnen und Leser!

Auf Grund des großen Erfolgs von EurActiv Deutschland findet die komplette deutschsprachige EU-Berichterstattung des EurActiv-Netzwerkes nun über Euractiv.de statt.

Die deutschsprachige Fassung von EurActiv.com wird nicht mehr aktualisiert, alle bisherigen übersetzten Texte bleiben aber im Archiv für Sie verfügbar.

Wir freuen uns, Sie künftig auf EurActiv.de begrüßen zu dürfen!

Rechnungsprüfer putzen EU wegen Galileo herunter

Veröffentlicht 01. Juli 2009 - Aktualisiert 29. Januar 2010
Druckoptimierte VersionEinem Freund senden

Die Führungsfähigkeiten der Europäischen Kommission wurden vom Rechnungsprüfungshof hart kritisiert, der das total verspätete Galileo-Satellitennavigationssystem der EU untersucht hatte.  Ein Bericht, der am 29. Juni veröffentlicht wurde, beschuldigt auch einzelne Mitgliedsstaaten dafür durchweg nur ihre wirtschaftlichen Interessen verfolgt zu haben. 

Galileo, the first industrial programme to be managed at European level, has been beset by long-running delays that have seen the project fail to meet deadlines. 

First suggested by the European Commission in 1994, the project involves the establishment of a network of navigational satellites to rival the Global Positioning System (GPS) run by the United States. 

The Court of Auditors report addressed the 2003–2006 period, when the project was managed by the Galileo Joint Undertaking (GJU), a body set up by the European Commission and the European Space Agency to manage the development and validation phase of the project. 

Management of this phase was judged "inadequate" by the Court's report, which concluded that the GJU "did not achieve most of its objectives". 

In a strong condemnation of the Commission's role in this multi-billion euro project, the Court's conclusions declared that the Commission "did not provide adequate leadership in developing and managing Galileo". 

While the Court found that the Galileo project had experienced problems "at different levels," the GJU's "most important task" was to negotiate a public-private partnership (PPP) investment deal, which stalled in early 2007. 

The Court found that the PPP was "inadequately prepared and conceived," and lays the blame with the Commission for requiring the GJU to negotiate a PPP which the auditors describe as "unrealistic". 

"The GJU did not achieve most of its objectives – owing, however, to factors that were largely outside the GJU's control," states the report. It found that the GJU's task was adversely affected by "governance issues, an incomplete budget, delays and the industrial organisation of the development and validation phase," issues for which the Commission receives much of the blame. 

A lack of clearly defined roles between member states, the Commission and other agencies also hindered the GJU's progess, and is the root of much of the Court's criticism of the EU executive. 

"The programme lacked a strong strategic sponsor and supervisor: the Commission did not proactively direct the programme, leaving it without a helmsman," states the Court's report. 

Member states also come in for criticism for putting the commercial interests of their own national industries ahead of the Galileo programme. 

"Owing to their different programme expectations, member states intervened in the interest of their national industries and held up decisions. The compromises made led to implementation problems, delays and, in the end, to cost overruns," noted the Court. 

Hintergrund : 

The Galileo satellite navigation system is Europe's civilian alternative to the US Global Positioning System (GPS) and the Russian GLONASS system, which are both funded and controlled by military authorities. 

The European Commission presented its initial plans in 1999, but the final agreement with EU member states was struck almost ten years later, in November 2007, after protracted discussions over the project's funding (see EurActiv LinksDossier). 